Discussion of Cleveland Union Terminal (Tower City Center).....

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

The state could have taken over the operation of this train at 100% federal funding for the first year, but it was committed to roads and was not interested. The high speed zealots out there at the time (Wilkowski & Co.) were not interested either, as the train did not fit their idea of high speed rail.

 

Thus, the train came off, Cleveland Union Terminal was abandoned and the railroad itself ripped up east of Mantua, a monumental loss and is unlikely to ever again be a passenger route. This stands as one of the most sordid chapters in Ohio's transportation history. Talk about myopia!!! :cry:

Link to comment
Share on other sites

I guess we can't cry over what we lost, but I do remember being in Cleveland in the early '70's and walking around what was the rail yards of Cleveland Terminal. The rails were still there, but were very rusty and the entire area was covered in a sea of weeds. The only trace of life was one track to the east and a platform used by the E-L commuter train to Youngstown. What a comedown for such a once-mighty facility!

 

I heard later that when the train did come off, Conrail was waiting with a work crew that ripped out the tracks immediately after the last train left. Of course, the platform area is now a parking deck, RTA has spread its tracks out at both ends of the station and now the Federal Court building sits at what was the west throat of the yard. We'll never get passenger trains in there again.

 

The only saving grace is that the lakefront location is a possibility, but even here, forces are at work which could jeopardize its usefulness.

Link to comment
Share on other sites

See aerial photo of the area here:

 

http://terraserver.microsoft.com/image.aspx?T=1&S=10&Z=17&X=2209&Y=22969&W=1&qs=West+3rd+and+Superior%7cCleveland%7cOhio%7c&Addr=W+3rd++W+Superior+Ave%2c+Cleveland%2c+OH+44113&ALon=-81.6954000&ALat=41.4988000

 

I'm speaking from solely an engineering perspective here, not necessarily a practical one:

 

Would it be possible to get rid of the two buildings by the Federal Justice Center (which would require buying out Sherwin-Williams-- probably impossible) and the stone building next to the draw bridge (an historical building, I know, but again, just speaking from an engineering perspective), then reconfigure Red Line bridge in order to bring tracks in there again? 

 

A very expensive proposition, I know, but it doesn't appear to be an engineering problem.  Or am I missing something?  When you consider that some urban freeway projects have cost as much as $120 million per mile, how far out of step would it be as far as cost?

Link to comment
Share on other sites

I found this interior shot of the Cleveland station, although it is for RTA trains, it's probably similiar to what the rest of the station looked like.  It was taken in the late 70's.  I wish I could have seen this city's passenger rail at it's peak...

Link to comment
Share on other sites

I didn't realize you were that hungry for any interior shots of Cleveland Union Terminal! I do have other interior shots of the railroad portion Cleveland Union Terminal -- I just don't have any of the E-L commuter train inside CUT.

 

So here's some views of Cleveland Union Terminal. Let's start outside and work our way in...

 

First, if you were on any of the 12-14 daily Erie passenger trains to/from Solon, Youngstown, Pittsburgh and New York City, or the six daily B&O trains to/from Akron, Youngstown, Pittsburgh and Washington DC, or the six daily Nickel Plate RR trains to/from Buffalo, or the 24 New York Central trains to/from Buffalo and New York Central.... this is the first hint that you were about to arrive at Cleveland Union Terminal. These are the east approach tracks to the station:

 

CUTEastapproachtracklevel1930.jpg

 

 

Some of the six station platforms and 12 tracks seen in 1930, shortly after the station opened:

 

CUTplatforms21930.jpg

 

 

West end of station:

 

CUTplatforms11930.jpg

 

 

East end of station (at left are Shaker RTS tracks):

 

CUTplatforms31930.jpg

 

 

One of the stairwells from track level to the station above:

 

CUTstairwell.jpg

 

 

Granted, these people are lining up in 1934 at CUT to see one of the many brand-new streamliners that will become common in the next decade or two. But, hey, it's a train at track level:

 

CUTtraininstation1934.jpg

 

 

These people are descending the stairwell from the station concourse to the track level so they can board New York Central's streamlined Mercury for Toledo and Detroit which rolled at 90 mph in some sections:

 

CUT_passengers_for_Mercury-s.jpg

 

 

No escalators were available as of July 17, 1945 to get from track level to the station concourse above, when a Cleveland newspaper published this cartoon urging the installation of escalators.  CUT was owned by a private company, the Cleveland Union Terminals Co., which could not afford to maintain the massive station complex despite the high usage fees assessed against the private railroads. CUT finally bowed to public pressure, adding them only to two stairwells and then only for travelers going up from track level.

 

CUTneedforstairs071745.jpg

 

 

Here is CUT's main concourse in 1930 when it was brand new. This view is looking north towards the rapid transit concourses and Public Square. The stairwells are in the middle of the floor:

 

CUTmainconcourseN1930.jpg

 

 

Main concourse looking south toward the Cuyahoga River in 1930:

 

CUTmainconcourseS1930.jpg

 

 

A south view in the main concourse in 1969 (remember the huge Welcome to Cleveland" mural?):

 

CUT_Concourse_5-3-69s.jpg

 

 

Looking north in 1980, on Cleveland Union Terminal's 50th anniversary:

 

CUT_Concourse_1980s.jpg

 

 

For those of you too young to remember Cleveland Union Terminal before it was completely reconfigured as Tower City Center, this how things were arranged prior to 1990:

 

CUTfloorplan1s.jpg

 

CUTcutaway1s.jpg

  • Love 1
  • Thanks 1

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

There's at least a half-dozen books on Cleveland Union Terminal, and several of those images were scanned from books about CUT or trains that served CUT.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

I think it's at the Western Reserve Historical Society.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

Look how well dressed everyone is in those photos.  People now ride airplanes in sandals and cut offs.

I've heard the mural is at the Western reserve Historical Society, but I wish they would put that somewhere it would have more relavence.  Put it at the Airport, or even back into Tower City somewhere.  Such a cool mural, made out of coated porcelin.  Really exudes the industrial muscle of the city.

On a weird note, I've owned the book "The Terminal Tower Complex, 1980" for many years, and for whatever reason the book smells like the station used to smell before it was renovated to Tower City.  I was only 7 when they started tearing up the station, but I swear that's what it smells like.  Maybe I'm out of my mind, whatever.

Nice pics though.

Link to comment
Share on other sites

OK, here's a couple more photos (thanks to the late Dave McKay) of a train that last ran 30 years ago today. Hard to believe it's been that long. Thanks to BuckeyeB and others for pointing out the losses that transcended the loss of this train (including most of the railroad line it used from Cleveland to Youngstown -- as well as the access to Cleveland Union Terminal).

 

May 1971 wasn't kind to the U.S. passenger rail industry. On May 1, Amtrak took over for the private railroads and, overnight, the U.S. lost half of its passenger trains. Cleveland went from 16 daily trains to two -- the eastbound and westbound Erie-Lackawanna commuter train. Here's the commuter leaving downtown Cleveland shortly after 5:20 p.m. on a May 1971 afternoon for Youngstown, paralleling the CTS and Shaker rapid tracks:

 

E-L_Commuter_skyline_May1971s.jpg

 

In the early 1970s, once you got east of Solon, you were in the countryside. My family moved to Bainbridge (one mile from the E-L line and Geauga Lake) in 1978, and it was still very rural back then. Today, it's McMansionland. East of Aurora toward Mantua, it was even more rural, and still is to some extent today. The commuter train's heaviest ridership was always between Cleveland and Aurora, diminishing to a handful of passengers left on board by the time it reached Youngstown. Here is the commuter train, zipping eastbound at 70 mph (track speed) by a water-filled sand quarry next to the intersection of Mennonite and Infirmary roads, between Aurora and Mantua, on May 12, 1972:

 

E-L_commuter_Mantua_5-12-72s.jpg

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

ah thanks for the pre-tower city terminal tower i well remember. my best memory was when i got a fake id there - hehe! glad to hear the mural still survives, although it should have stayed up in the mall there somewhere.

 

funny ive been looking at tokyo stations and info all day while watching football, we are going this summer. this thread is a sad followup. our government just cant seem to see the relationship between a healthy region and fantastic public transit.

Link to comment
Share on other sites

I think the mural should be incorporated into the interior design of whatever station facility is built in Cleveland to serve the Ohio Hub and future commuter trains. 

 

I think the same thing should be done with the surviving arch from the exterior of the demolished Columbus Union Station.

 

At the very least, it acknowledges our history and the mistakes of the past.

Link to comment
Share on other sites

I think the mural should be incorporated into the interior design of whatever station facility is built in Cleveland to serve the Ohio Hub and future commuter trains. 

 

I think the same thing should be done with the surviving arch from the exterior of the demolished Columbus Union Station.

 

At the very least, it acknowledges our history and the mistakes of the past.

 

wasn't that what the 670 cap was designed for? (har har)

Link to comment
Share on other sites

Hey Noozer! That's a terrific idea to use the mural and the arch also!! Let's not forget that. Maybe we can have a "Hall of Shame" to commemorate all the stupid things we've done over the last 50 years. :roll:

 

you guys can put them all inside of Detroit's Michigan Central Station

Link to comment
Share on other sites

KJP, thanks for the great pics!  As a 20-something, my earliest memory of CUT was during the Tower City renovation.  I have always been curious to know what it looked like when it was an actual train station.

 

Would it be possible to get rid of the two buildings by the Federal Justice Center (which would require buying out Sherwin-Williams-- probably impossible) and the stone building next to the draw bridge (an historical building, I know, but again, just speaking from an engineering perspective), then reconfigure Red Line bridge in order to bring tracks in there again?

 

While I'm not a railway engineer, per se, I worked on a feasibility study on the elevated rail structures in the train shed at Richmond (VA) Main Street Station (1901).  There had been some intentional destruction of the structure in the 1980s, not to mention 105 years of deterioration.  The results of our analysis showed that even if restored to the original design, the structures would not be capable of supporting the loads of a modern passenger train.

 

Back when the Red Line bridge was built (anyone have a date???), train design loads were much lower.  I suspect that you would have to undertake significant structural reinforcement of the bridge to carry a modern passenger train, to the point where it would probably be cheaper to build a new bridge from scratch. 

Link to comment
Share on other sites

... Back when the Red Line bridge was built (anyone have a date???), ...

 

The "Red Line" bridge was built as part of the Terminal Tower project, and completed about 1929, I think. It was the western approach to Union Terminal for mainline passenger trains. Although steam locomotives didn't run into the terminal, the electric locomotives that pulled passenger trains through the terminal were pretty massive and many of the railroads still ran six-axle heavyweight cars as sleepers and parlor cars during the era that the bridge was in mainline service.

 

I would expect that it would be up to the task, provided it's structurally sound and up to its design specs.

 

Here's a shot from when things were at their lovliest, in 1979. It looks like the bridge is wide enough to have carried three tracks. You can see one end of the pre-tower-city concourse in this photo.

w_rr_appr_to_term_tower_1979.jpg

Link to comment
Share on other sites

I would expect that it would be up to the task, provided it's structurally sound and up to its design specs.

 

See my point above.  If I had to render a professional opinion, I would say the bridge as-is is inadequate for supporting a modern passenger train.  One must also consider that in that time period, there were no design considerations for fatigue of the structure due to cyclic loading, which is now required unless the Structural Engineer of Record wants to lose his license should something go wrong. 

 

There are other implications as well, in the design loads for lurching (longitudinal) and tracking (lateral) loads.  The nature of railroad bridge design involves a whole slew of dynamic considerations, and when you increase the base design load to modern loading (per the American Railway Engineers Association), the dynamic loads are magnfied as well.  The combination of increased stresses can quickly overcome an outdated design.

 

 

Link to comment
Share on other sites

I'll bet the bridge is still suitable for passenger trains. It has been in continuous and well maintained and was recently rehabilitated for about $22 million. I think you should look at the bridge from below to determine its condition. There are numerous steel and concrete bridges around Greater Cleveland that are less substantial yet carry loaded coal trains (each loaded coal car weighs up to 125 tons).

 

And, actually, steam locomotives did operate into Cleveland Union Terminal on a fairly regular basis, including New York Central's massive Niagara locomotives that probably weighed 200 tons (nearly twice the weight of today's heaviest freight cars loaded). New York Central's "Mercury" between Cleveland and Detroit routinely kept its steam locomotive to avoid the time spent switching electric for steam at Linndale, and vice-versa upon its return in the afternoon. Here's a rendering, but accurate:

 

NYC%20Mercury%20CUT%201930s%20small.jpg

 

I also have a book showing a Nickel Plate RR freight train hauled by a large Berkshire steam locomotive detouring via CUT due to a derailment. I'll scan it sometime and post it. It's pretty cool to see.

 

And, yes, passenger trains could physically return to CUT, but at a price. It would require rerouting the Red Line north on or under West 25th to Detroit Avenue, then on the subway deck of the Detroit-Superior high-level bridge, and then enter CUT with a short crossover. Also, the Waterfront Line's inbound ramp to Tower City would have to be kept at a lower level for a little longer distance (250 feet?) so passenger train tracks could travel above it.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

And, yes, passenger trains could physically return to CUT, but at a price. It would require rerouting the Red Line north on or under West 25th to Detroit Avenue, then on the subway deck of the Detroit-Superior high-level bridge, and then enter CUT with a short crossover. Also, the Waterfront Line's inbound ramp to Tower City would have to be kept at a lower level for a little longer distance (250 feet?) so passenger train tracks could travel above it.

 

This is what I thought.  It's not an engineering problem, it's one of price and institutional barriers, plus an important operating consideration:  at one point some years ago, Amtrak said that using CUT would increase the running time of the Lake Shore Limited by 1/2 hour. 

 

It's a shame it was lost, but at this point, we're probably better off with pursuing the Lakefront Bypass and building a nice, new station (possibly along with an expanded convention center) at its current location.

Link to comment
Share on other sites

A fantasy - flesh out more of the Burnham Group Plan with the proposed Union Depot. The site overlooks the location of the present Amtrak station:

 

(image linked from CSU site, http://www.csuohio.edu/CUT/UT1903.jpg)

UT1903.jpg

 

I either forgot or never knew about the Mercury running into CUT under steam. Imagine that -- someone actually cared about keeping a tight passenger schedule! I wonder what sort of hoops they had to jump through to get permission to run steam through there.

Link to comment
Share on other sites

They would back the Mercury into the western side of the station just far enough that the steam locomotive was outside of the station. That way, the soot wouldn't get into the station.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

Haven't I seen renderings of a proposed civic center / convention center facility that would span the tracks and run down to the lakefront in the area of the present Amtrak station? I envision a handsome structure at the end of the mall with a neoclassical-derived design facing the mall and a glassed-in facade and atrium on the north side giving a view of the lakefront, with escalators and elevators going down to track level.

Link to comment
Share on other sites

Haven't I seen renderings of a proposed civic center / convention center facility that would span the tracks and run down to the lakefront in the area of the present Amtrak station? I envision a handsome structure at the end of the mall with a neoclassical-derived design facing the mall and a glassed-in facade and atrium on the north side giving a view of the lakefront, with escalators and elevators going down to track level.

 

yes, there were renderings. that would or could happen if the old convention center, partly under the mall there, is chosen to be redeveloped (versus building an all new cc behind tower city). fingers crossed!

 

 

Link to comment
Share on other sites

Rob_1412 says:

 

"I envision a handsome structure at the end of the mall with a neoclassical-derived design facing the mall and a glassed-in facade and atrium on the north side giving a view of the lakefront, with escalators and elevators going down to track level."

 

Well now I need to take a trip to Cleveland to look at the area!

 

I like the idea of a neoclassical building fronting the mall, harmoniously blending with City Hall and other buildings as Rob_1412 suggests. The beauty of this idea is that in one stroke we connect the lakefront with downtown, tying in the convention center and have a world-class entrance to Cleveland.

 

KJP and I discussed things like this a while back and I think it's an idea that makes sense. By tying all these things together, we can spread the costs also. KJP, didn't you have a diagram of this idea?

 

Terrific idea!! :clap:

Link to comment
Share on other sites

And, yes, passenger trains could physically return to CUT, but at a price. It would require rerouting the Red Line north on or under West 25th to Detroit Avenue, then on the subway deck of the Detroit-Superior high-level bridge, and then enter CUT with a short crossover. Also, the Waterfront Line's inbound ramp to Tower City would have to be kept at a lower level for a little longer distance (250 feet?) so passenger train tracks could travel above it.

 

It's ashame planners lacked the vision to possibly restore commuter/Amtrak trains back to their natural terminal at Tower City by RTA's (on the Cuyahoga viaduct) and the Stokes Fed Court building's blocking such (what!? Cleveland lack courage and vision toward public transit??? no!!)... Unfortunately, the above scenario which would screw around with the Rapid is unacceptable.  Such re-routing the Red Line would result in surface running along W. 25 for the airport line, and that would simply be stupid ... Better to focus on developing the North Coast station near where Dan Burnham originally projected it...

 

... btw gildone, do you have any insight on the Lakefront freight bypass you alluded to which could free up tracks for commuter even Rapid rail?

 

 

Link to comment
Share on other sites

Yes, I have one, as well as a conceptual proposal by the city for the convention center/intermodal station over the tracks. I'll see if I can find it sometime, but I wouldn't post it here to make futile attempt to get this thread back on topic.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

^looks like space for about 8 tracks + platforms (besides the 2 RTA tracks).  An overhead, multi-modal-transfer station with escalators, elevators and TOD/air-rights development seems like exactly what the doctor ordered for this location.

Link to comment
Share on other sites

You could probably have four tracks with no problem, which would be plenty. The two nearest tracks are the NS main and they would surely object to their use as a part of a passenger station.

 

So in order, going north to south you'd have:

 

2 RTA tracks====================================

 

1 station track (now a mostly unused siding)------------------------------

        Existing platform

1 Existing track (currently used by Amtrak)-----------------------------------

1 Reconstructed former Conrail main track, now CSX------------------------

        New platform

1 New track in area between CSX and NS tracks-----------------------------

 

2 NS mainline tracks================================

 

Pardon my primitive diagram.... :-D

Link to comment
Share on other sites

 

... btw gildone, do you have any insight on the Lakefront freight bypass you alluded to which could free up tracks for commuter even Rapid rail?

 

Well, I was alluding to KJP's Lakefront Bypass study that he did a couple of years ago.  So technically, all the insight is his  :-D

Link to comment
Share on other sites

That is a very attractive building and I would love to see it get built to complete the group plan (especially since I love neoclassical buildings). I get that the first floor and lower levels would me mainly lobby and baggage "stuff", but what was to be housed on the upper floors of that large building?

Link to comment
Share on other sites

You could probably have four tracks with no problem, which would be plenty. The two nearest tracks are the NS main and they would surely object to their use as a part of a passenger station.

 

 

Unless trains are going to layover in the station, three tracks would probably be sufficient for the Ohio Hub.

Link to comment
Share on other sites

Did Cleveland or Cincinnati have commuter service the way Chicago did, with locals running to a point out in the suburbs and then returning (for example in Chicago the Milwaulkee Road running a commuter service to Fox Lake or Elgin,but no further), or was rail commuting done via routine longer-distance "local" trains, that had convenient schedules that permitted commuting?

 

 

 

Link to comment
Share on other sites

... but what was to be housed on the upper floors of that large building?

 

Probably railroad and station offices, possibly commercial office space, too.

 

Edit: I added a photo to my previous post, showing what arriving passengers would see when they exited the station at mall level.

Link to comment
Share on other sites

Here's a link to more information about the Lakefront Bypass (including links to view the full report):

 

http://www.ecocitycleveland.org/ecologicaldesign/blue/rail_bypass_sum.html

 

Did Cleveland or Cincinnati have commuter service the way Chicago did, with locals running to a point out in the suburbs and then returning (for example in Chicago the Milwaulkee Road running a commuter service to Fox Lake or Elgin,but no further), or was rail commuting done via routine longer-distance "local" trains, that had convenient schedules that permitted commuting?

 

Not sure about Cincinnati, but Cleveland had a number of local passenger trains (as opposed to expresses) that originated in outlying areas (Ashtabula, Norwalk, Akron, Alliance and Youngstown), made stops at virtually every station along the route and arrived in downtown Cleveland before 9 a.m. They then departed downtown between 4-6 p.m. and headed back to the outlying area from whence they came. In addition to the E-L commuter to Youngstown, Pennsylvania Railroad had a Cleveland - Alliance train via Bedford, Macedonia, Hudson and Ravenna that lasted until 1964.

 

As for the lakefront intermodal hub, RTA paid for a study of it in the mid-1990s. I have a copy of the report with renderings in it, but this first image is what was proposed. The images following were done by the city, showing different levels of a combined intermodal hub and convention center, starting from the track level and going upward.

 

Looking east....

Cleveland%20lakefront%20rendering%20MBC%202-27-01%201.jpg

 

Track level....

ConvCtrLevel580-2.jpg

 

Main concourse level....

ConvCtrLevel620-2.jpg

 

Street level....

ConvCtrLevel650-2.jpg

 

Looking north toward the lake and the tracks, basically where the rendering circa 1900 (shown earlier) was looking...

 

MallConventionCenter.jpg

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

By the way, there is more information about this site at:

 

http://www.conventioncleveland.com/la.html

 

See the fourth bulleted item from the top and click on the graphics at the right side of the page. Too bad the Tower City site will be favored for a convention center and medical mart as long as Jackson is mayor and Forest City Enterprises keeps bankrolling his campaigns.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

Too bad the Tower City site will be favored for a convention center and medical mart as long as Jackson is mayor and Forest City Enterprises keeps bankrolling his campaigns.

 

That doesn't preclude planning for an appropriate rail station on the lakefront.

Link to comment
Share on other sites

That's what I'm saying. What's happening at Tower City leaves the lakefront as the only area left for building a train station in downtown Cleveland.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

Oh, gotcha.  I misinterpreted your comment to mean that the convention center was an integral part of a lakefront train station.

 

Let's be honest, though.  As great as it would be to have "CUT" again, there's no way the federal government is going to tear down that crappy courthouse.  I would rather look toward the lakefront to build a new station, preferably harmonious with and sensitive to the Burnham plan, and where there aren't as many geographic constraints to capacity.

 

Off the top of my head, considering the existing Amtrak long-distance service, proposed Ohio Hub service (in which Cleveland would be THE hub of the network), Midwest High Speed Rail, and potential commuter rail, I guess a new station would require at least six tracks.  This doesn't include room for storage or yards.  Realistically, this level of service could make Cleveland at least as busy a rail station as Baltimore Penn Station, which has six tracks, so I think anything less would be short-sighted.

 

 

Link to comment
Share on other sites

They wouldn't have to tear down the federal courthouse. One of these days, I need to put my concept on paper for restoring train service to Tower City Center. It would, however, require ripping out the parking level added between the station platforms and Tower City above.

“What is the meaning of this city? Do you huddle close together because you love each other?”
Or “We all dwell together to make money from each other”? -- TS Eliot’s The Rock

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recently Browsing   0 members

    • No registered users viewing this page.
×
×
  • Create New...